PM 8 Production Hall, Koehler Paper
Completed in 2019
247m
Hall Length
about27m
Hall Height
approximately13,900m²
Floor area
01OurServices
Construction carried out by the MKE Group.
- MKE Group Services
- Construction of Hall PM 8 and the Roller Warehouse
- Time period
- 2018 to 2019
- Architecture
- Schweiker Architekten und archigroup
Construction work was performed by the MKE Group. Project development, planning, and investment were handled by third parties.
02Gallery
Views.
03Overview
At the Kehl Rhine Port, the facility for Koehler Paper's Production Line 8 has been completed—the largest single investment in the company's history.
The facility houses a paper machine and a coating machine. Less than two years passed between the groundbreaking in May 2018 and the production of the first roll of paper in October 2019.
04Profile
The facts at a glance.
- Location
- Kehl Rhine Port, Koehler Paper Plant
- Usage
- Production Hall with Roller Bearing
- Product
- Flexible Packaging and Barrier Papers
- Commissioning
- October 2019
Next Project · Achern
Care and Housing at the Glassworks